Jimah will supply electricity to Tenaga Nasional Berhad
(TNB) for a 25
year period via a Power Purchase Agreement (PPA).
Our commercial operation date of unit 1 of 700MW was
achieved on 1st January 2009 and unit 2 on 1st July
2009.
The Plant is located in Mukim Jimah, Daerah Port
Dickson, Negeri Sembilan is capable of providing a
total of 1,400 MW (net) to the Grid System. |
| |
|
 |
| |
The two (2) coal fired generating Units, each
with a nominal capacity of 700 MW, equipped for
clean coal technology with electrostatic
precipitators
and flue
gas desulphurisation (FGD) plants. The Units will
be supported by common systems including a coal
handling system with its adjoining coal yard, a
chimney, an ash disposal lagoon, a once-through
cooling water system as well as power plant
buildings, workshops and warehouses.
Imported coal will be received and stored by the
fuel facilites via conveyors, leading to the Plant
coalbunkers. Coal for the Plant is expected to be
imported mainly from Australia, Indonesia, China and
other countries within the region having coal of
similar properties. Electricity produced by the
Plant is exported via the generator transformers to
the Interconnection Facilities that are connected to TNB's Grid System. |
| |
|
 |
| |
Site Location :
The project is located at Mukim Jimah, District of Port
Dickson, Negeri Sembilan Darul Khusus. The site is
situated on a beach front facing the Straits of
Malacca, adjacent to the mouth of Sungai Sepang on
the eastern side.
The nearest towns to the Project site are Sepang in
Selangor and Port Dickson in Negeri Sembilan. The site is approximately fifteen (15) kilometres from Sepang and twenty (20) kilometres
from Port Dickson. |
| |
|
 |
| |
Application for alienation of the land was
approved by the state authority on 7th January 2005. The project site
is designated as “Gunatanah Perindustrian” and a
potential site for reclamation. It is located in
“Block Perancangan 3”, where a specific provision is
made on the admissibility of the construction of
Jimah IPP (Aktiviti-Aktiviti Yang Dibenarkan, page
3-40, Rancangan Tempatan Lukut 1999-2005). The local
plan also specifically mentions that the development
is subject to an EIA study and conditions provided
for therein.
The project site is located partly on the seawater
reclamation and mangrove area facing the Straits of
Malacca. The sea bed level generally varies from RL:+0.0m
MLSD to RL:-2.5m MLSD. At the mangrove area, the
ground level generally varies from RL:+0.8m MLSD to
RL:+1.5m MLSD.
Power Plant is constructed on the mud-flat area
which platform level with shore protection has been reclaimed to +5.4m MLSD. |
| |
| |
|
 |